! colspan="2"|August
 +
|-
 
|'''Week of August 20th'''
 
|'''Week of August 20th'''
 
|
 
|
Line 11: Line 13:
 
*Research on new technology solutions begins.
 
*Research on new technology solutions begins.
 
*'''Initial IGVC pre-planning meeting and research on new technology solutions begins.'''
 
*'''Initial IGVC pre-planning meeting and research on new technology solutions begins.'''
 +
|-
 +
! colspan="2"|September
 
|-
 
|-
 
|'''Week of September 3rd'''
 
|'''Week of September 3rd'''
Line 28: Line 32:
 
|
 
|
 
*Technology solutions are finalized and design work begins.
 
*Technology solutions are finalized and design work begins.
 +
|-
 +
! colspan="2"|October
 
|-
 
|-
 
|'''Week of October 1st'''
 
|'''Week of October 1st'''
Line 48: Line 54:
 
|
 
|
 
*Begin work on initial implementation.
 
*Begin work on initial implementation.
 +
|-
 +
! colspan="2"|November
 
|-
 
|-
 
|'''Week of November 5th'''
 
|'''Week of November 5th'''
Line 64: Line 72:
 
|
 
|
 
*On board testing and demonstration of first design iteration.
 
*On board testing and demonstration of first design iteration.
 +
|-
 +
! colspan="2"|December
 
|-
 
|-
 
|'''Week of December 3rd'''
 
|'''Week of December 3rd'''
Line 84: Line 94:
 
|
 
|
 
*Independent design work may be pursued.
 
*Independent design work may be pursued.
 +
|-
 +
! colspan="2"|January
 
|-
 
|-
 
|'''Week of January 7th'''
 
|'''Week of January 7th'''
Line 100: Line 112:
 
|
 
|
 
*Backup implementation and testing period of first iteration.
 
*Backup implementation and testing period of first iteration.
 +
|-
 +
! colspan="2"|February
 
|-
 
|-
 
|'''Week of February 4th'''
 
|'''Week of February 4th'''
Line 116: Line 130:
 
|
 
|
 
*Secondary design phase.
 
*Secondary design phase.
 +
|-
 +
! colspan="2"|March
 
|-
 
|-
 
|'''Week of March 3rd'''
 
|'''Week of March 3rd'''
Line 136: Line 152:
 
|
 
|
 
*On board testing, optimization, and full systems integration.
 
*On board testing, optimization, and full systems integration.
 +
|-
 +
! colspan="2"|April
 
|-
 
|-
 
|'''Week of April 7th'''
 
|'''Week of April 7th'''
Line 152: Line 170:
 
|
 
|
 
*Final exams week – no work expected.
 
*Final exams week – no work expected.
 +
|-
 +
! colspan="2"|May
 
|-
 
|-
 
|'''Week of May 5th'''
 
|'''Week of May 5th'''
Line 168: Line 188:
 
|
 
|
 
*Last minute implementation, optimization, and testing.
 
*Last minute implementation, optimization, and testing.
 +
|-
 +
! colspan="2"|June
 
|-
 
|-
 
|'''Week of June 2nd'''
 
|'''Week of June 2nd'''

Revision as of 18:23, 1 September 2007

Here is a nearly week-by-week schedule that we hope to stick to throughout the year. Each month, key members will meet to review documentation and progress that has been made. We will compare our actual progress against the plan and attempt to alleviate any sluggishness in development. Expected results will appear in normal font - actual results will appear in bold.

August
Week of August 20th
  • Initial IGVC pre-planning meeting.
  • General RJ pre-planning meeting.
Week of August 27th
  • Research on new technology solutions begins.
  • Initial IGVC pre-planning meeting and research on new technology solutions begins.
September
Week of September 3rd
  • New members are welcomed and are guided into filling necessary positions.
  • At this time, dues should be paid and wiki accounts signed up.
Week of September 10th
  • Research continues.
Week of September 17th
  • Research continues.
Week of September 24th
  • Technology solutions are finalized and design work begins.
October
Week of October 1st
  • Design work continues.
Week of October 8th
  • Design work continues.
Week of October 15th
  • Design work continues.
Week of October 22nd
  • Finish design work and purchase necessary components.
Week of October 29th
  • Begin work on initial implementation.
November
Week of November 5th
  • Implementation continues.
Week of November 12th
  • Implementation continues.
Week of November 19th
  • On board testing and demonstration of first design iteration.
Week of November 26th
  • On board testing and demonstration of first design iteration.
December
Week of December 3rd
  • Dead week – no work expected.
Week of December 10th
  • Final exams week – no work expected.
Week of December 17th
  • Independent design work may be pursued.
Week of December 24th
  • Independent design work may be pursued.
Week of December 31st
  • Independent design work may be pursued.
January
Week of January 7th
  • Evaluation of current progress – have we kept up with the plan?
Week of January 14th
  • Backup implementation and testing period of first iteration.
Week of January 21st
  • Backup implementation and testing period of first iteration.
Week of January 28th
  • Backup implementation and testing period of first iteration.
February
Week of February 4th
  • Backup implementation and testing period of first iteration.
Week of February 11th
  • Secondary design phase.
Week of February 18th
  • Secondary design phase.
Week of February 25th
  • Secondary design phase.
March
Week of March 3rd
  • Secondary design phase.
Week of March 10th
  • Implementation of secondary design features.
Week of March 17th
  • Implementation of secondary design features.
Week of March 24th
  • Implementation of secondary design features.
Week of March 31st
  • On board testing, optimization, and full systems integration.
April
Week of April 7th
  • On board testing, optimization, and full systems integration.
Week of April 14th
  • On board testing, optimization, and full systems integration.
Week of April 21st
  • Dead week – no work expected.
Week of April 28th
  • Final exams week – no work expected.
May
Week of May 5th
  • Documentation gathered. Design paper and presentation prepared.
Week of May 12th
  • Last minute implementation, optimization, and testing.
Week of May 19th
  • Last minute implementation, optimization, and testing.
Week of May 26th
  • Last minute implementation, optimization, and testing.
June
Week of June 2nd
  • 16th Annual Intelligent Ground Vehicle Competition!