IGVC 2008 General Schedule and Progress Review
Here is a nearly week-by-week schedule that we hope to stick to throughout the year. Each month, key members will meet to review documentation and progress that has been made. We will compare our actual progress against the plan and attempt to alleviate any sluggishness in development.
Contents
- 1 Week of August 20th
- 2 Week of August 27th
- 3 Week of September 3rd
- 4 Week of September 10th
- 5 Week of September 17th
- 6 Week of September 24th
- 7 Week of October 1st
- 8 Week of October 8th
- 9 Week of October 15th
- 10 Week of October 22nd
- 11 Week of October 29th
- 12 Week of November 5th
- 13 Week of November 12th
- 14 Week of November 19th
- 15 Week of November 26th
- 16 Week of December 3rd
- 17 Week of December 10th
- 18 Week of December 17th
- 19 Week of December 24th
- 20 Week of December 31st
- 21 Week of January 7th
- 22 Week of January 14th
- 23 Week of January 21st
- 24 Week of January 28th
- 25 Week of February 4th
- 26 Week of February 11th
- 27 Week of February 18th
- 28 Week of February 25th
- 29 Week of March 3rd
- 30 Week of March 10th
- 31 Week of March 17th
- 32 Week of March 24th
- 33 Week of March 31st
- 34 Week of April 7th
- 35 Week of April 14th
- 36 Week of April 21st
- 37 Week of April 28th
- 38 Week of May 5th
- 39 Week of May 12th
- 40 Week of May 19th
- 41 Week of May 26th
- 42 Week of June 2nd
Week of August 20th
Expected Result
- Initial IGVC pre-planning meeting.
Actual Progress
- General RJ pre-planning meeting.
Week of August 27th
Expected Result
- Research on new technology solutions begins.
Actual Progress
- Initial IGVC pre-planning meeting and research on new technology solutions begins.
Week of September 3rd
Expected Result
- New members are welcomed and are guided into filling necessary positions.
- At this time, dues should be paid and wiki accounts signed up.
Week of September 10th
Expected Result
- Research continues.
Week of September 17th
Expected Result
- Research continues.
Week of September 24th
Expected Result
- Technology solutions are finalized and design work begins.
Week of October 1st
Expected Result
- Design work continues.
Week of October 8th
Expected Result
- Design work continues.
Week of October 15th
Expected Result
- Design work continues.
Week of October 22nd
Expected Result
- Finish design work and purchase necessary components.
Week of October 29th
Expected Result
- Begin work on initial implementation.
Week of November 5th
Expected Result
- Implementation continues.
Week of November 12th
Expected Result
- Implementation continues.
Week of November 19th
Expected Result
- On board testing and demonstration of first design iteration.
Week of November 26th
Expected Result
- On board testing and demonstration of first design iteration.
Week of December 3rd
Expected Result
Dead week – no work expected.
Week of December 10th
Expected Result
Final exams week – no work expected.
Week of December 17th
Expected Result
Independent design work may be pursued.
Week of December 24th
Expected Result
Week of December 31st
Expected Result
Week of January 7th
Expected Result
Evaluation of current progress – have we kept up with the plan?
Week of January 14th
Expected Result
Backup implementation and testing period of first iteration.
Week of January 21st
Expected Result
Week of January 28th
Expected Result
Week of February 4th
Expected Result
Week of February 11th
Expected Result
Secondary design phase.
Week of February 18th
Expected Result
Week of February 25th
Expected Result
Week of March 3rd
Expected Result
Week of March 10th
Expected Result
Implementation of secondary design features.
Week of March 17th
Expected Result
Week of March 24th
Expected Result
Week of March 31st
Expected Result
On board testing, optimization, and full systems integration.
Week of April 7th
Expected Result
Week of April 14th
Expected Result
Week of April 21st
Expected Result
Dead week – no work expected.
Week of April 28th
Expected Result
Final exams week – no work expected.
Week of May 5th
Expected Result
Documentation gathered. Design paper and presentation prepared.
Week of May 12th
Expected Result
Last minute implementation, optimization, and testing.